Al-Fayha’a Bridge
The Al-Fayha’a Bridge in Basra, Iraq, is composed of
two main bridges. Those bridges, called West and East
bridges, are connected on the Sindibad Island.
The East bridge has been bombed in 1991.
Setraco was awarded the contract for a range of works, including:
Repositioning of the displaced six spans, cast of the destroyed four spans,
supply and fix the Pot Bearings and supply and fix the Expansion joints.
The Incremental Launching method of construction is used.
This method of construction can be used for bridges having constant cross
section shape throughout their length.
The Incremental Launching
method has several advantages.
It eliminates the traditional
scaffolding required for supporting
the formwork. This is particularly
valuable for projects spanning over
deep water as in this case. Most
of the construction operations take
place in the same location. The
pre-casting work is thus more easily
supervised, giving a high quality.
Setraco is the first and only
contractor to use this method in
Iraq, after it was used in the same
project, in the late 80’s.